|
HEYSHAM-M6 LINK, NORTHERN ROUTE SUMMARY Transport Solutions for Lancaster and Morecambe (TSLM) commissioned a review of the case for the Heysham-M6 Link Northern Route submitted by Lancashire County Council to DfT for Programme Entry as a LTP Major Scheme. The review has found significant flaws in the presentation, in particular in the Major Scheme Business Case and its Annexes. The conclusion is that the scheme should be rejected, because of failings in both the scheme itself and the appraisal process as set out in WebTAG guidance. The main issues are:- Failure to fulfil overall objectives Of the four overall objectives, the proposal only partially satisfies one (faster journey times to the Port of Heysham), which benefits only 2.5% of traffic on the network. On the other three:
Failure to follow appraisal guidance The most significant failing in the bid is to follow WebTAG appraisal guidance in many areas. The most important of these are:-
A central concept of the NATA approach, of a systematic working towards an optimum solution, with an audit trail explaining each decision at each stage, is absent. Regional issues RPG 13 does not call for a new road link to the port of Heysham, but for improvements to the road link. Its policies point towards new road construction being the option of last resort, with the emphasis on making best use of existing infrastructure, maximising the potential for modal transfer, incorporating all modes into solutions, and only considering roads after a thorough examination of all possible solutions. Lancashire CC have not provided evidence that they have done all these things: even a claim in the MSBC that they have a track record on sustainable transport falls short of integration into the solution, since almost all ‘soft measures’ are happening independently of the new road proposal, and are separately funded. An improved link to Heysham is a regional transport priority, but in the recent regional prioritisation exercise the Northern Route proposal failed to make the top quartile of regional priority transport schemes. It appears to be in effect the 18th highest priority out of 72 schemes in NW England. Public consultation The main issues have been covered under appraisal guidance above. Specific shortcomings in such consultation as did occur are reported by TSLM in the appendix to the main report. Traffic modelling There are many issues of detail, but the main point is that the implied long-term reduction in traffic levels on existing roads purported to be relieved by the Northern Route is at odds with recent experience of traffic effects of new roads. In a situation where there is serious congestion, and at least 70% of existing traffic will not reassign to the new road because it does not serve those trips, it is illusory to pretend that traffic levels will not rise back towards the current situation fairly rapidly, especially in the absence of significant demand management measures fully integrated into the solution. In any case, many local roads are not relieved to any extent. Scheme design The treatment of the M6 junction area is extremely convoluted and does not come across as a good design solution. It almost certainly contributes to the very high scheme cost of £118 million (and rising). Cost issues
Conclusion The Heysham-M6 Link Northern Route is the product of a decision making process which decided a long time ago that a new road was the solution to accessibility problems on the Morecambe/ Heysham peninsula. The choice lay between a western and northern route, and once the western route was decisively rejected in 2004 the northern route became the preferred scheme. Although current appraisal guidance calls for in effect a “blank sheet” at the start of the process of defining a preferred option for new LTP major schemes, with a wide range of possible solutions, no preferred modal solution in mind, and a requirement to explore synergies between different types of solution, this was never the case with the current proposal. As a solution to current congestion problems on the local road network the Northern Route is futile. The wide range of possible solutions involving less drastic, and less damaging, increases in road capacity have not been adequately identified and appraised, and until this is done there should be no question of this scheme proceeding any further. |
|||
|
Download the full Report (132 Kb pdf file) here
|
|||